Our study with Princeton University’s ZERO Lab and encoord, supported by Google, models six real data center sites in a PJM utility’s territory to show how flexible grid connection and bring-your-own capacity (BYOC) get large loads to full power years faster without shifting costs to other customers.
3–5 years faster to grid power. A 500 MW data center can reach full operation in roughly two years.
Grid power available for more than 99% of all hours. On-site resources were dispatched just 40–70 hours per year.
Data centers cover their own incremental costs. Flexible grid connection and BYOC offset nearly 100% of the net system cost increase from new load.
A repeatable blueprint. Utilities already have the data and planning tools to run this analysis today.